Consortium · United Arab Emirates (Middle East)
Altair (Orbitworks, Abu Dhabi)
Altair-1, the program's first satellite, launched on SpaceX Transporter-18 on 1 Oct 2026 with NVIDIA GPUs and is commissioning; edge class. Its next announced step is the other nine satellites of the first ten, stated as through 2027.
Stage 5 of 7: Own satellite flown
Altair-1, the program's first satellite, launched on SpaceX Transporter-18 on 1 Oct 2026 with NVIDIA GPUs and is commissioning; edge class.[1][2]
What the stage means: Its own compute satellite flown.
DoneReported
IHC acquires 80% of Marlan Space
Source: Via Satellite
DoneConfirmed
$1B Altair program signed in Paris; first 10 satellites in production
Partners: Mistral AI, BlackSky; MaiaSpace preferred launcher.
Sources: Orbitworks; DatacenterDynamics
DoneConfirmed
Altair-1 launched on Transporter-18; signal acquired, commissioning
Built by Orbitworks with NVIDIA GPUs. Edge class.
Sources: SatellitePro ME; TechAfrica News; NewSpace Economy
Targets as the organisation stated them. When a date moved, every move is listed with its source; a narrower window is shown as a narrowing.
through 2027
about five years
Deploy the 50-satellite constellation[1]
What to watch · SpaceNexus note, not a prediction
Whether Altair-1 completes commissioning and returns data, and whether the other nine of the first ten satellites follow through 2027.
| Figure | Value | Confidence and source |
|---|---|---|
| Planned satellites | 50 satellites | Company claim[1] |
| Program value | 1 USD billion (program investment, not a funding round) | Company claim[1][2] |
Pierre-Damien Vaujour (CEO, Loft Orbital) · Hamdullah Mohib (CEO, Marlan Space and Orbitworks) · Syed Basar Shueb (CEO, IHC)
| Program | Stage | Confirmed funding | Next step |
|---|---|---|---|
| Altair (this page) | Stage 5 of 7: Own satellite flown | Not counted | 2027: The other nine satellites of the first ten |
| Aethero | Stage 5 of 7: Own satellite flown | $8.4M | Q2 2027: Titan: NVIDIA Thor compute cluster on EnduroSat FRAME-15 |
| Google Suncatcher | Stage 5 of 7: Own satellite flown | Not counted | 2027: Two-satellite mission testing inter-satellite laser links |
| KP Labs | Stage 5 of 7: Own satellite flown | Not counted | 2027: Leopard DPU on ESA OPS-SAT VOLT |
| Orbital Chenguang | Stage 5 of 7: Own satellite flown | Not counted | 2025 to 2027: First computing constellation and key technologies |
| Planet | Stage 5 of 7: Own satellite flown | Not counted | 2027: Pair of Suncatcher satellites with Google |
| Space String | Stage 5 of 7: Own satellite flown | Not counted | Q4 2027: G1 verification satellite (11.5 kW compute payload) |
APA
SpaceNexus. (2026, November 2). Altair constellation (Loft Orbital, Marlan Space, Orbitworks), Orbital Data Centers: Tracker entry [Data set]. Retrieved November 2, 2026, from https://spacenexus.us/orbital-data-centers/altair-loft-marlan
Chicago
SpaceNexus. "Altair constellation (Loft Orbital, Marlan Space, Orbitworks), Orbital Data Centers: Tracker entry." Data as of November 2, 2026. Accessed November 2, 2026. https://spacenexus.us/orbital-data-centers/altair-loft-marlan.
BibTeX
@misc{spacenexus_altairconstellationloftorbitalma_2026,
author = {{SpaceNexus}},
title = {{Altair constellation (Loft Orbital, Marlan Space, Orbitworks), Orbital Data Centers}: Tracker entry},
year = {2026},
month = nov,
howpublished = {\url{https://spacenexus.us/orbital-data-centers/altair-loft-marlan}},
url = {https://spacenexus.us/orbital-data-centers/altair-loft-marlan},
urldate = {2026-11-02},
note = {Data as of 2026-11-02; each fact links its primary source}
}Evidence reviewed 2 Nov 2026, fact-checked against primary sources. Nothing on this page is sponsored, and no company can pay to change, reorder or preview it. Spotted an error? Report a correction. How stages and labels work.
Week in Space Data, every Friday.