US vs China · Moon race tracker
Who is winning the race to the Moon, China or the US? As of 24 Sep 2026, United States leads on demonstrated milestones toward a crewed landing (China 1.75, United States 3.5, out of 8 rungs; a lead needs a full rung). The two are level on demonstrated milestones toward a permanent presence (China 1.25, United States 1, out of 8 rungs; a lead needs a full rung). Who lands people first is too close to call: under the published rule a country is projected first only if its window ends before the other’s begins in every scenario, and that is not the case today.
Official targets: China, before 2030 (2030年前); United States, 2028 (NASA target: early 2028) with Artemis IV. More answers
Level on demonstrated milestones · China 1.25 · United States 1 of 8
Level on demonstrated milestones (China 1.25 · United States 1 of 8). Crewed-landing projection: Too close to call. Illustration: positions are schematic. Each site stands for a programme; partners’ assets count toward the programme whose architecture includes them. Select any structure for its evidence.
| Rung | China · ILRS | United States · Artemis |
|---|---|---|
| P1 South-polar robotic landing (Robotic lander) | ¼: Integrated ground or atmospheric test (blueprint) | ½: Flown, short of the criterion (under construction) |
| P2 Dedicated lunar relay (Relay satellite) | 1: Complete (built) | 0: Planned (ghost footprint) |
| P3 ISRU demonstrated on the Moon (Resource plant (ISRU)) | 0: Planned (ghost footprint) | ½: Flown, short of the criterion (under construction) |
| P4 Power through the lunar night (Night power unit) | 0: Planned (ghost footprint) | 0: Planned (ghost footprint) |
| P5 Crew-capable surface habitat (Pressurised habitat) | 0: Planned (ghost footprint) | 0: Planned (ghost footprint) |
| P6 Cadence (Two crew landing pads) | 0: Planned (ghost footprint) | 0: Planned (ghost footprint) |
| P7 30-day crewed stay (Crew, rover and tracks) | 0: Planned (ghost footprint) | 0: Planned (ghost footprint) |
| P8 Continuous presence, one year (Outpost beacon (crewed all year)) | 0: Planned (ghost footprint) | 0: Planned (ghost footprint) |
| L1 Landing launchers reach orbit | ½: Flown, short of the criterion (under construction) | ½: Flown, short of the criterion (under construction) |
| L2 Crew vehicle: uncrewed lunar round trip | ½: Flown, short of the criterion (under construction) | 1: Complete (built) |
| L3 Crew beyond low Earth orbit | ¼: Integrated ground or atmospheric test (blueprint) | 1: Complete (built) |
| L4 Crew lander flown in space | ¼: Integrated ground or atmospheric test (blueprint) | ½: Flown, short of the criterion (under construction) |
| L5 Critical in-space operations | 0: Planned (ghost footprint) | ½: Flown, short of the criterion (under construction) |
| L6 Uncrewed landing by the crew lander | ¼: Integrated ground or atmospheric test (blueprint) | 0: Planned (ghost footprint) |
| L7 Lunar surface suit flown | 0: Planned (ghost footprint) | 0: Planned (ghost footprint) |
| L8 Crewed landing | 0: Planned (ghost footprint) | 0: Planned (ghost footprint) |
| Totals | Moon base 1.25 of 8 · Crewed landing 1.75 of 8 | Moon base 1 of 8 · Crewed landing 3.5 of 8 |
A neutral tracker of the United States and China, built on a published method, beside a catalogue of every lunar mission since the first attempts of 1958. It separates two questions: who has demonstrated more of the hardware, and who is projected to land first. Every rung, date and number links to its source.
Data reviewed against sources as of · Tracker method v1.0.3 · All dates UTC unless a local time is shown
At least one person on the lunar surface, returned to Earth alive.
United States leads on demonstrated milestones (China 1.75 · United States 3.5 of 8; a lead needs a full rung)
Too close to call
Headline scenario (lunar + human-spaceflight record, remaining-horizon model): bands overlap. 7 of 12 scenarios give the same call; the rest are listed on the method page. Low confidence.
Mengzhou-1: uncrewed debut on Long March 10A, docking at Tiangong
Official plan: 2026 (CMSA mission-patch notices, Oct/Nov 2025). Not in CMSA’s February 2026 annual plan; in May CMSA spoke of verifying the Earth-orbit system "over the next two years through multiple space-station flights".
Sources: China Manned Space Agency (CMSE site) (28 Oct 2025) · China Manned Space Agency (CMSE site) (26 Nov 2025)
Starship Flight 14: the first Starship to reach orbit
"Splashdown confirmed ... the first orbital flight of Starship" (SpaceX, 28 Sep 2026). Liftoff time from Launch Library 2.
SpaceX reports that the ship entered orbit, deployed all 26 Starlink V3 satellites it carried (all in contact), then made a deorbit burn and splashed down in the Pacific after about 3 hours in orbit; the booster splashed down in the Gulf. The first 13 flights were all suborbital. The ship was Starlink-configured, a variant of the family, so reaching orbit does not move rung L1 on its own (method v1.0.3).
Sources: SpaceX on X (28 Sep 2026) · SpaceX on X (28 Sep 2026) · Space.com (updated 17 Sep 2026)
The tracker scores crewed landing and permanent presence separately. As of 24 Sep 2026: United States leads on demonstrated milestones toward a crewed landing (China 1.75, United States 3.5, out of 8 rungs; a lead needs a full rung). The two are level on demonstrated milestones toward a permanent presence (China 1.25, United States 1, out of 8 rungs; a lead needs a full rung). Who lands people first is too close to call: under the published rule a country is projected first only if its window ends before the other’s begins in every scenario, and that is not the case today.
Embed code
<iframe src="https://spacenexus.us/embed/moon-race" width="100%" height="330" style="border:0;max-width:560px" title="Race to the Moon: US vs China tracker (SpaceNexus)" loading="lazy"></iframe>
The card shows both ladders, the projection call and the official targets, and updates when the tracker does. Data licence: CC BY 4.0.
Preview
Open the card as it appears when embedded (opens in a new tab).
Prefer an image? PNG or SVG of the tracker, with the attribution drawn in.
Licence: this data is published under CC BY 4.0 (Creative Commons Attribution 4.0 International). Use it, share it and adapt it, commercially too, with credit to SpaceNexus and a link. It is our own compilation from the public sources linked on every row; quoted statements and those sources remain their owners’, and the illustrations are not part of the dataset.
Suggested citation
SpaceNexus. (2026). Race to the Moon: US vs China lunar tracker (Version 2026-09-24) [Data set]. https://doi.org/10.5281/zenodo.22985974. Licensed CC BY 4.0.
@misc{spacenexus_moon_tracker_20260924,
author = {{SpaceNexus}},
title = {Race to the Moon: US vs China lunar tracker},
year = {2026},
version = {2026-09-24},
howpublished = {\url{https://spacenexus.us/moon}},
doi = {10.5281/zenodo.22985974},
note = {Licensed CC BY 4.0},
}Version 2026-09-24: the date the data was last reviewed against its sources. Persistent identifier: https://doi.org/10.5281/zenodo.22985974.
| Item | China | United States |
|---|---|---|
| Launches per landing Sources: NASA Office of Inspector General (IG-26-004) (10 Mar 2026) · Spaceflight Now (10 Mar 2026) · SpaceNews (Jul 2023) | Two Long March 10s | SLS plus "more than 10 Starship tankers" (OIG; Spaceflight Now says 10 to 20) |
| Published lunar budget Sources: SpacePolicyOnline (3 Apr 2026) · The Planetary Society (24 Mar 2026) |

Continuous human occupation of a lunar surface site for at least 365 days.
Level on demonstrated milestones (China 1.25 · United States 1 of 8; a lead needs a full rung)
China is ahead on L6, P2.United States is ahead on L2, L3, L4, L5, P1, P3.The tracker counts only confirmed events. China usually announces tests after they happen; NASA and US companies announce target dates in advance.
Download the tracker as one chart: SVG or PNG (1200 × 630, attribution included). The dates behind the windows: the promise ledger.
CN · China
Official target: Before 2030 (2030年前)
Projected: central 18 Nov 2029; window 30 May 2029 – 27 Oct 2032 (n = 5)
Sources: China Manned Space Agency (CMSE site) (29 May 2023) · China Manned Space Agency (CMSE site) (27 Feb 2026) · China Manned Space Agency (CMSE site) (23 May 2026)
US · United States
Official target: 2028 (NASA target: early 2028) for Artemis IV
Projected: central 20 Nov 2030; window 14 Nov 2029 – 22 Jul 2031 (n = 4)
Sources: NASA (RELEASE 26-022) (27 Feb 2026) · NASA ESDMD (3 Mar 2026) · NASA (updated 16 Mar 2026) · U.S. GAO (GAO-26-108556) (23 Jul 2026)
No projection is shown for permanent presence: neither official target defines continuous crewing. United States: EO 14369: "establishing initial elements of a permanent lunar outpost by 2030". NASA’s Moon Base phase plan starts long-duration human presence in 2033 or later. No official date for continuous occupation. China: ILRS "basic model" by 2035: "an expandable and maintainable system capable of long-term robotic operation with short-term human participation". No official date for continuous occupation.
Wangyu suit "final prototype"
Yang Liwei, around 6 Jan 2026 (China in Space, 7 Jan 2026; secondary)
Sources: China in Space (7 Jan 2026, secondary)
Starship HLS uncrewed lunar landing demonstration
Must include a lunar ascent. OIG (March 2026): expected "to slip to the end of 2026" at the earliest. It depended on first orbit, which Starship reached on 28 Sep 2026 (Flight 14), and still depends on ship-to-ship transfer.
Sources: NASA Office of Inspector General (IG-26-004) (10 Mar 2026)
New Glenn return to flight
Sources: Spaceflight Now (30 Jun 2026)
Griffin Mission One ("Moon Base II")
Lander plus Astrolab’s FLIP rover for the Nobile crater region near Mons Mouton, near the south pole, 10 payloads in all; the only lunar launch NASA expects in 2026. Falcon Heavy per Spaceflight Now. Voyager Technologies completed its acquisition of Astrobotic on 13 Jul 2026.
Sources: Aerospace America (AIAA) (15 Sep 2026) · NASA (updated 1 Sep 2026) · NASA Science (updated 6 May 2026) · Voyager Technologies (13 Jul 2026) · Spaceflight Now (16 Jun 2026) · NASA (release 26-046) (26 May 2026)
ESA interim ministerial in Italy, where "greater clarity" on ESA’s Artemis role "could come"
Interim meetings do not approve programme funding (European Spaceflight).
Sources: European Spaceflight (23 Jun 2026)
FY2027 continuing resolution runs out
NASA is funded at FY2026 levels until then
Sources: Computing Research Association (3 Sep 2026)
Blue Moon MK1 "Endurance" ("Moon Base I")
Uncrewed cargo pathfinder (not the crew lander) for the Shackleton connecting ridge, carrying NASA’s SCALPSS cameras and a laser retroreflector. The slip followed the New Glenn explosion on its pad in May 2026.
Sources: Aerospace America (AIAA) (15 Sep 2026) · NASA (release 26-046) (26 May 2026) · Spaceflight Now (30 Jun 2026)
IM-3 Nova-C "Trinity" ("Moon Base III")
Reiner Gamma swirl (Lunar Vertex). NASA had said 2026 on 26 May 2026.
Sources: Aerospace America (AIAA) (15 Sep 2026) · NASA (release 26-046) (26 May 2026) · NASA Science (updated 6 May 2026)
From Launch Library 2 via our launch schedule; dates there can move daily. Dates are shown only as precisely as Launch Library gives them, and a launch our sync has not refreshed for 3 days is left off.
NASA expects only one lunar launch in 2026 (Griffin-1)
Sources: Aerospace America (AIAA) (15 Sep 2026)
Chang’e-7 postponed out of this year’s window
CMSA: “In line with the principle of being prudent, reliable and failure-proof, and after a comprehensive assessment, the Chang’e-7 mission does not meet launch conditions and cannot be carried out in this year’s planned window.” No cause and no new date given.
Sources: China Manned Space Agency (CMSE site) (23 Aug 2026) · Xinhua (23 Aug 2026) · CBS News (23 Aug 2026)
Chang’e-7 and Long March 5 Y14 rolled out to the pad
Sources: China Manned Space Agency (CMSE site) (19 Aug 2026)
Method: v1.0.3 published 24 Sep 2026. See the changelog.
Who lands people first is too close to call: under the published rule a country is projected first only if its window ends before the other’s begins in every scenario, and that is not the case today. In the headline scenario the central projected landing dates are: United States 20 Nov 2030 (window 14 Nov 2029 to 22 Jul 2031); China 18 Nov 2029 (window 30 May 2029 to 27 Oct 2032). Official targets: China, before 2030 (2030年前); United States, 2028 (NASA target: early 2028) with Artemis IV.
Sources: NASA (RELEASE 26-022) (27 Feb 2026) · NASA ESDMD (3 Mar 2026) · NASA (updated 16 Mar 2026) · U.S. GAO (GAO-26-108556) (23 Jul 2026) · China Manned Space Agency (CMSE site) (29 May 2023) · China Manned Space Agency (CMSE site) (27 Feb 2026) · China Manned Space Agency (CMSE site) (23 May 2026)
The last crew left the lunar surface on 14 Dec 1972 (Apollo 17). Artemis II flew four astronauts around the Moon, launching on 1 Apr 2026. The next planned landings are Artemis IV, dated 2028 (NASA target: early 2028), and China’s first crewed landing, dated before 2030 (2030年前).
Sources: NASA (20 Apr 2026) · NASA (mission blog) (6 Apr 2026) · NASA (RELEASE 26-022) (27 Feb 2026) · NASA ESDMD (3 Mar 2026) · China Manned Space Agency (CMSE site) (23 May 2026)
China’s official target is a first crewed landing before 2030 (2030年前). Two Long March 10 launches; Mengzhou and the two-seat Lanyue lander meet in lunar orbit. CMSA, 23 May 2026: go all out to achieve, "on schedule" (如期), the first Chinese landing before 2030. No launch sequence has been officially dated.
Sources: China Manned Space Agency (CMSE site) (23 May 2026) · China Manned Space Agency (CMSE site) (27 Feb 2026) · China Manned Space Agency (CMSE site) (14 Jun 2024) · SpaceNews (Jul 2023)
Artemis IV, dated 2028 (NASA target: early 2028). Four crew; two descend near the lunar south pole. Artemis III, dated 2027 (NASA target: mid-2027), is a crewed docking test with lander pathfinders in Earth orbit, not a landing.
Sources: NASA (RELEASE 26-022) (27 Feb 2026) · NASA ESDMD (3 Mar 2026) · NASA (updated 16 Mar 2026) · U.S. GAO (GAO-26-108556) (23 Jul 2026) · NASA Office of Inspector General (IG-26-004) (10 Mar 2026)
The International Lunar Research Station, led by China and Russia. ILRS "basic model" by 2035: "an expandable and maintainable system capable of long-term robotic operation with short-term human participation". No official date for continuous occupation. China’s space agency counts 17 countries and international organizations, as well as more than 50 international research institutions (stated 23 Apr 2025).
Sources: China National Space Administration (Xinhua) (24 Apr 2025) · gov.cn (Xinhua) (7 Sep 2024) · China National Space Administration (Xinhua) (24 Apr 2025)
75 countries as of September 2026, on NASA’s list of signatories. The most recent is Côte d’Ivoire, on 24 Sep 2026.
Neither official target defines continuous crewing, so the tracker makes no projection for it. United States: EO 14369: "establishing initial elements of a permanent lunar outpost by 2030". NASA’s Moon Base phase plan starts long-duration human presence in 2033 or later. No official date for continuous occupation. China: ILRS "basic model" by 2035: "an expandable and maintainable system capable of long-term robotic operation with short-term human participation". No official date for continuous occupation.
Sources: The White House (Executive Order 14369) (18 Dec 2025) · SpaceQ (24 Mar 2026) · gov.cn (Xinhua) (7 Sep 2024) · China National Space Administration (Xinhua) (24 Apr 2025)
| No published figure found. We do not estimate one. |
| Artemis request $8.5 billion for FY2027; Moon Base about $20 billion over seven years (as presented) |
| Partners | ILRS: “17 countries and international organizations, as well as more than 50 international research institutions” (CNSA, 24 Apr 2025) | Artemis Accords: 75 signatories (NASA) |
|---|
| Robotic and crewed landings (from our catalogue) | 4 upright soft landings; 0 tipped; 0 crashed; 0 crewed | 6 upright robotic soft landings; 2 tipped; 2 crashed; 6 crewed (Apollo) |
|---|
Evidence last reviewed 24 Sep 2026. Found an error? Tell us; corrections are logged on the method page.