Startup ยท United States
formerly Lumen Orbit
Starcloud has flown one 60 kg satellite carrying an NVIDIA H100 and holds the most verified funding of any company in the field, $443.4M across five rounds. Every step after the demonstrator depends on launch access and on thermal hardware that has not flown: Starcloud-2 has moved from October 2026 to 2027.
Shared launches: Bandwagon-4 (2025-11-02) with Astro Digital, NVIDIA.
Stage 5 of 7: Own satellite flown
Starcloud-1, a 60 kg satellite carrying one NVIDIA H100, launched on 2 Nov 2025.[1]
What the stage means: Its own compute satellite flown.
DoneConfirmed
$2.4M pre-seed as Lumen Orbit; demonstrator promised for May 2025
The demonstrator target was restated in December 2024 and the satellite flew on 2 Nov 2025, about six months later.
Sources: Payload; TechCrunch
DoneConfirmed
$11M seed as Lumen Orbit
Seed out of Y Combinator S24; reported $40M valuation.
Sources: TechCrunch; GeekWire
DoneConfirmed
$10M seed extension and rebrand to Starcloud
Total seed $21M; renamed from Lumen Orbit.
Sources: DatacenterDynamics; American Bazaar; Cosmic Log
DoneConfirmed
Crusoe agrees to run Crusoe Cloud on a Starcloud satellite
At the time the satellite was scheduled for late 2026, with limited GPU capacity offered from early 2027.
Sources: Crusoe; DatacenterDynamics
DoneConfirmed
Starcloud-1 launched with an NVIDIA H100
60 kg satellite on an Astro Digital Corvus-Micro+ bus, launched on SpaceX Bandwagon-4 (Falcon 9). Orbit about 495 x 503 km; still in orbit as of 3 Oct 2026.
Sources: Gunter's Space Page; US SEC; CelesTrak
DoneCompany claim
Gemma inference and nanoGPT training on Starcloud-1
Company says it ran Google Gemma and trained a small nanoGPT model on the works of Shakespeare; reported by CNBC on 10 Dec 2025. Not independently verified.
DoneConfirmed
FCC application for up to 88,000 satellites
Distributed data center constellation with laser links; accepted for filing 13 Mar 2026.
Sources: SpaceNews; Communications Daily; FCC
DoneConfirmed
$170M Series A at $1.1B valuation
Led by Benchmark and EQT Ventures.
Sources: Payload; Via Satellite
DoneCompany claim
Starlink Mini laser terminal contract
More than 50 terminals across at least 25 satellites, up to 25 Gbps links (company release as quoted by Unite.AI).
Source: Unite.AI
DoneConfirmed
$250M Series A extension at $2.3B valuation
Led by Manhattan West; NVIDIA and Cisco Investments joined. About 25 employees and a Woodinville, WA factory.
Sources: TechCrunch; Via Satellite; SiliconANGLE
DoneConfirmed
Firefly signs Starcloud SC-1L lunar-orbit compute payload
SC-1L rides Firefly Elytra on Blue Ghost Mission 3, NET 2028.
Sources: Firefly Aerospace; GlobeNewswire
Targets as the organisation stated them. When a date moved, every move is listed with its source; a narrower window is shown as a narrowing.
2027Slipped once
Two Starcloud-2 satellites (8 kW each) on rideshare[1][2][3]
Moved: October 2026 to 2027[1]
early 2027 (set October 2025; at risk, tied to Starcloud-2, now 2027)
2028 to 2029 (CEO expects Starship access then)
Starcloud-3: 200 kW, about 3 t, deployed from Starship[1]
NET 2028
SC-1L lunar-orbit compute demo on Firefly Elytra (Blue Ghost Mission 3)[1]
What to watch ยท SpaceNexus note, not a prediction
Whether the two Starcloud-2 satellites launch in 2027, and whether Crusoe opens in-orbit GPU capacity after they do.
Dated promises with two sources for the promise and the outcome. No grades or ratings.
| Step | Promised | Outcome | Moved by |
|---|---|---|---|
| First demonstrator (Starcloud-1) | May 2025, said 11 Mar 2024[1][2] | Launched 2 Nov 2025[1] | 5 to 6 months |
| Starcloud-2 launch | October 2026, said 30 Mar 2026[1][2] | Now 2027 (stated 21 Aug 2026)[1] | 3 to 15 months |
| Figure | Value | Confidence and source |
|---|---|---|
| Starcloud-1 mass | 60 kg | Confirmed[1] |
| GPUs on Starcloud-1 | 1 NVIDIA H100 | Confirmed[1] |
| Starcloud-2 power per satellite (planned) | 8 kW | Company claim[1] |
| Starcloud-3 power (planned) | 200 kW | Company claim[1] |
| FCC filing, maximum satellites | 88,000 satellites | Reported[1] |
| Valuation after Series A extension | $2.3B | Reported[1] |
Rounds come from company announcements, regulatory filings and press reports. Amounts, valuations and investors are as reported and may be incomplete or later revised. Not investment advice, and not an offer or solicitation for any security. Full disclaimer
| Date | Round | Amount |
|---|---|---|
| 11 Mar 2024 | Pre-seed (as Lumen Orbit)Counted in the tracker total.[1][2] | $2.4M |
| 11 Dec 2024 | Seed (as Lumen Orbit). Led by NFX (lead); Y Combinator (accelerator) and othersCounted in the tracker total.[1][2] | $11M |
| 26 Feb 2025 | Seed extension (SAFE)Counted in the tracker total.[1][2][3] | $10M |
| 30 Mar 2026 | Series A ($1.1B valuation). Led by Benchmark, EQT VenturesCounted in the tracker total.[1][2] | $170M |
| 21 Aug 2026 | Series A extension ($2.3B post-money). Led by Manhattan WestNVIDIA's participation is reported; the size of its share comes from one anonymous source (TechCrunch, citing a person familiar with the deal)..Counted in the tracker total.[1][2][3] | $250M |
Philip Johnston (co-founder, CEO) ยท Ezra Feilden (co-founder, CTO) ยท Adi Oltean (co-founder)
| Program | Stage | Verified funding | Next step |
|---|---|---|---|
| Starcloud (this page) | Stage 5 of 7: Own satellite flown | $443.4M | 2027: Two Starcloud-2 satellites (8 kW each) on rideshare |
| Aethero | Stage 5 of 7: Own satellite flown | $8.4M | Oct 2026: Titan: Jetson Thor compute cluster on EnduroSat FRAME-15 |
| Altair | Stage 5 of 7: Own satellite flown | Not counted | 2027: The other nine satellites of the first ten |
| Google Suncatcher | Stage 5 of 7: Own satellite flown | Not counted | 2027: Two-satellite mission testing inter-satellite laser links |
| KP Labs | Stage 5 of 7: Own satellite flown | Not counted | Mid-2026: Leopard DPU on ESA OPS-SAT VOLT |
| Orbital Chenguang | Stage 5 of 7: Own satellite flown | Not counted | 2025 to 2027: First computing constellation and key technologies |
| Planet | Stage 5 of 7: Own satellite flown | Not counted | 2027: Pair of Suncatcher satellites with Google |
Evidence reviewed 5 Oct 2026, fact-checked against primary sources. Nothing on this page is sponsored, and no company can pay to change, reorder or preview it. Spotted an error? Report a correction. How stages and labels work.