Promise Ledger
United States space agency. These are the dated public commitments by NASA and its people that we could source to a primary, with what happened.
15 entries: 4 met; 1 missed; 9 revised; 1 withdrawn.
Plain counts, not a grade or a ranking. A short record is not a complete one. Checked against sources on Sep 26, 2026; scoring rules on the methodology page.
This first release is a selection, and a short record is not a complete record. Each programme milestone enters the ledger at its earliest dated public commitment we can find in a primary source, for governments and companies alike. Later dated commitments for the same milestone are shown on that one entry as a revision chain, oldest first, rather than as separate entries.
Includes statements by: Jim Bridenstine
Revised · worded as a commitment
First flight · NASA
“a launch readiness schedule based on an initial SLS flight no later than November 2018”
Said . Source: NASA: NASA Completes Key Review of World’s Most Powerful Rocket in Support of Journey to Mars (RELEASE 14-229) (Aug 27, 2014, paragraph 2)
Context: SLS Key Decision Point C commitment. Exploration Mission-1 was renamed Artemis I in 2019. The same release quotes William Gerstenmaier: "will be ready no later than November 2018."
Later dated commitments for the same milestone
The counts use the original commitment. The latest date in the chain stands as: met late.
Outcome: SLS lifted off on the uncrewed Artemis I mission at 1:47 a.m. EST on 2022-11-16 from Launch Pad 39B. (, 261 days after the latest deadline)
Outcome source: NASA: Liftoff! NASA’s Artemis I Mega Rocket Launches Orion to Moon (RELEASE 22-117) (Nov 16, 2022)
Checked against the source on Sep 26, 2026. Report a correction or send a response to this entry
Revised · worded as a commitment
Landing · Jim Bridenstine, NASA Administrator · NASA
“Next year, our initial science and technology research will be on the lunar surface”
Said . Source: NASA: NASA Selects First Commercial Moon Landing Services for Artemis Program (May 31, 2019, paragraph 2 (Bridenstine quote))
Context: Said when NASA announced its first three CLPS lander task orders.
Later dated commitments for the same milestone
The counts use the original commitment. The latest date in the chain stands as: met late.
Outcome: Intuitive Machines' IM-1 (Odysseus) touched down in the lunar South Pole region on 2024-02-22 with NASA instruments aboard; NASA describes IM-1 as the mission "which landed, tipped over, and operated on the lunar surface". (, 783 days after the latest deadline)
Outcome source: NASA: Fourth Launch of NASA Instruments Planned for Near Moon's South Pole (Feb 26, 2025)
Checked against the source on Sep 26, 2026. Report a correction or send a response to this entry
Missed · worded as a commitment
Launch cadence · NASA
“using commercial delivery services to send dozens of new science investigations and technology demonstrations to the Moon twice per year beginning in 2021”
Said . Source: NASA: NASA Publishes Artemis Plan to Land First Woman, Next Man on Moon in 2024 (RELEASE 20-092) (Sep 21, 2020, paragraph 4)
Context: Artemis Plan release. The sentence begins "NASA already will be back on the Moon robotically".
Outcome: No CLPS mission launched in 2021, 2022 or 2023. Intuitive Machines' IM-1, carrying NASA instruments, touched down on 2024-02-22. No NASA statement moving the 2021 start was found.
Outcome source: NASA: NASA Collects First Surface Science in Decades via Commercial Moon Mission (Mar 1, 2024)
Checked against the source on Sep 26, 2026. Report a correction or send a response to this entry
Revised · worded as a target
Station or module · NASA
“NASA is targeting launch of the power and propulsion element on a commercial rocket in late 2022.”
Said . Source: NASA: NASA Awards Artemis Contract for Lunar Gateway Power, Propulsion (RELEASE 19-042) (May 23, 2019, paragraph 3)
Context: Release on the Maxar power and propulsion element award. In 2020 NASA combined the element with the habitation and logistics outpost (HALO) for a single launch.
Later dated commitments for the same milestone
The counts use the original commitment. The latest date in the chain stands as: pending.
Outcome: No Gateway element had launched as of 2026-09-26. GAO’s 2026 assessment lists Gateway Initial Capability among the projects NASA announced plans to pause.
Outcome source: U.S. Government Accountability Office: NASA: Assessments of Major Projects (GAO-26-108556) (Jul 23, 2026)
Checked against the source on Sep 26, 2026. Report a correction or send a response to this entry
Revised · worded as a commitment
Crewed milestone · NASA
“a commitment to be ready for a launch with astronauts no later than April 2023”
Said . Source: NASA: NASA Completes Key Milestone for Orion Spacecraft in Support of Journey to Mars (RELEASE 15-185) (Sep 16, 2015, paragraph 2)
Context: Orion Key Decision Point C (KDP-C) commitment. The first crewed mission, then called Exploration Mission-2 (EM-2), was renamed Artemis II in 2019.
Later dated commitments for the same milestone
The counts use the original commitment. The latest date in the chain stands as: met.
Outcome: SLS lifted off from Launch Pad 39B at Kennedy Space Center at 6:35 p.m. EDT on 2026-04-01 with four astronauts aboard Orion. (, on or before the latest deadline)
Outcome source: NASA: Liftoff! NASA Launches Astronauts on Historic Artemis Moon Mission (RELEASE 26-026) (Apr 1, 2026)
Checked against the source on Sep 26, 2026. Report a correction or send a response to this entry
Revised · worded as a target
Crewed milestone · NASA (NASA (with Boeing))
“NASA and Boeing’s Crew Flight Test (CFT), planned no earlier than July 21, 2023, is the first crewed flight of the Starliner system”
Said . Source: NASA (Commercial Crew blog): NASA Updates Commercial Crew Planning Manifest Through 2024 (Apr 14, 2023, section: NASA's Boeing Crew Flight Test)
Context: NASA commercial crew planning manifest, published with partners Boeing and SpaceX.
Later dated commitments for the same milestone
The counts use the original commitment. The latest date in the chain stands as: met.
Outcome: The Crew Flight Test launched with Butch Wilmore and Suni Williams at 10:52 a.m. ET on 2024-06-05 (Boeing). Starliner returned uncrewed in September 2024 and the two astronauts returned on SpaceX Crew-9 in March 2025 (NASA, 2026-02-19). ()
Outcome source: Boeing: Boeing Starliner Spacecraft Completes Successful Launch (Jun 5, 2024)
Checked against the source on Sep 26, 2026. Report a correction or send a response to this entry
Met · worded as a target
Crewed milestone · NASA
“NASA and SpaceX are targeting mid-August for the launch of Crew-7”
Said . Source: NASA (Commercial Crew Program blog): NASA, SpaceX Target Mid-August for Crew-7 Launch (Apr 5, 2023, paragraph 1)
Outcome: Crew-7 launched at 3:27 a.m. EDT on 2023-08-26 from Launch Complex 39A and reached orbit. (, on or before the deadline)
Outcome source: NASA: NASA’s SpaceX Crew-7 Launches to International Space Station (RELEASE 23-094) (Aug 26, 2023)
Checked against the source on Sep 26, 2026. Report a correction or send a response to this entry
Met · worded as a target
Launch · NASA
“Psyche, also a robotic mission, is targeted to launch in October of 2023”
Said . Source: NASA: NASA Selects Two Missions to Explore the Early Solar System (RELEASE 17-003) (Jan 4, 2017, paragraph 4)
Context: NASA release selecting Lucy and Psyche for the Discovery Program. The launch was later moved earlier to 2022, then back to October 2023.
Later dated commitments for the same milestone
The counts use the original commitment. The latest date in the chain stands as: met.
Outcome: Psyche launched on a Falcon Heavy from Kennedy Space Center on 2023-10-13. (, on or before the deadline)
Outcome source: NASA: Launching to a Metal-Rich Asteroid (Oct 16, 2023)
Checked against the source on Sep 26, 2026. Report a correction or send a response to this entry
Revised · worded as a target
Crewed milestone · NASA
“NASA’s SpaceX Crew-8: NET February 2024”
Said . Source: NASA (Commercial Crew Program blog): NASA Updates Commercial Crew Planning Manifest Through 2024 (Apr 14, 2023, Target Launch Manifest list)
Context: NASA commercial crew planning manifest.
Later dated commitments for the same milestone
The counts use the original commitment. The latest date in the chain stands as: met.
Outcome: Crew-8 launched at 10:53 p.m. EST on 2024-03-03 (03:53 UTC on 2024-03-04) from Launch Complex 39A and reached orbit. (, on or before the latest deadline)
Outcome source: NASA: NASA’s SpaceX Crew-8 Launches to International Space Station (RELEASE 24-035) (Mar 3, 2024)
Checked against the source on Sep 26, 2026. Report a correction or send a response to this entry
Met · worded as a commitment
Launch · NASA
“The Europa Clipper mission will launch in October 2024 on a Falcon Heavy rocket”
Said . Source: NASA: NASA Awards Launch Services Contract for Europa Clipper Mission (Jul 23, 2021, paragraph 2)
Outcome: Europa Clipper launched on a Falcon Heavy from Launch Complex 39A at 12:06 p.m. EDT on 2024-10-14. (, on or before the deadline)
Outcome source: NASA: Liftoff! NASA's Europa Clipper Sails Toward Ocean Moon of Jupiter (Oct 14, 2024)
Checked against the source on Sep 26, 2026. Report a correction or send a response to this entry
Withdrawn · worded as a target
Landing · NASA
“NASA has requested the Astrobotic and VIPER mission teams to adjust VIPER’s delivery to the Moon’s South Pole to November 2024.”
Said . Source: NASA: NASA Replans CLPS Delivery of VIPER to 2024 to Reduce Risk (Jul 18, 2022, paragraph 1)
Context: VIPER was to land on Astrobotic's Griffin lander under CLPS; it had been scheduled for November 2023.
Outcome: On 2024-07-17 NASA announced its intent to discontinue VIPER development, citing cost increases, launch delays and the risk of further cost growth. On 2025-09-19 NASA awarded Blue Origin a CLPS task order with an option to deliver VIPER to the lunar South Pole in late 2027 on a second Blue Moon MK1 lander (RELEASE 25-064); no delivery took place in November 2024.
Outcome source: NASA: NASA Ends VIPER Project, Continues Moon Exploration (Jul 17, 2024)
Checked against the source on Sep 26, 2026. Report a correction or send a response to this entry
Revised · worded as a commitment
Landing · Jim Bridenstine, NASA Administrator · NASA
“We are tasked with landing on the Moon’s South Pole by 2024.”
Said . Source: NASA: NASA Administrator Statement on Return to Moon in Next Five Years (RELEASE 19-022) (Mar 26, 2019, statement, paragraph 1)
Context: Statement after Vice President Mike Pence’s announcement at the fifth National Space Council meeting; the landing later became the Artemis III mission.
Later dated commitments for the same milestone
The counts use the original commitment. The latest date in the chain stands as: pending.
Outcome: No crewed landing on the Moon's South Pole took place by the end of 2024. NASA's 2026-02-27 update moved Artemis III to 2027 as a low Earth orbit test mission and planned the first landing for Artemis IV in 2028.
Outcome source: NASA: NASA Adds Mission to Artemis Lunar Program, Updates Architecture (RELEASE 26-022) (Feb 27, 2026)
Checked against the source on Sep 26, 2026. Report a correction or send a response to this entry
Revised · worded as a target
Launch · NASA (NASA (with Boeing))
“NASA and Boeing are targeting no earlier than April 2026 to fly the uncrewed Starliner-1 pending completion of rigorous test, certification, and mission readiness activities.”
Said . Source: NASA (Commercial Crew blog): NASA, Boeing Modify Commercial Crew Contract (Nov 24, 2025, paragraph 2)
Context: Announced with a contract modification that set the firm Starliner order at four missions.
Later dated commitments for the same milestone
The counts use the original commitment. The latest date in the chain stands as: pending.
Outcome: Starliner-1 had not launched by 2026-09-26. On 2026-05-01 NASA said its launch opportunities "remain under review as teams continue working through technical issues discovered during the Crew Flight Test in 2024"; Boeing's 10-Q filed 2026-07-28 says it now expects to complete an uncrewed mission no earlier than the fourth quarter of 2026.
Outcome source: NASA (Commercial Crew blog): NASA, Partners Update International Space Station 2026 Flight Plan (May 1, 2026)
Checked against the source on Sep 26, 2026. Report a correction or send a response to this entry
Revised · worded as a commitment
Launch · NASA
“Dragonfly will launch in 2026 and arrive in 2034.”
Said . Source: NASA: NASA’s Dragonfly Will Fly Around Titan Looking for Origins, Signs of Life (RELEASE 19-052) (Jun 27, 2019, paragraph 2)
Context: NASA release selecting Dragonfly as the fourth New Frontiers mission.
Later dated commitments for the same milestone
The counts use the original commitment. The latest date in the chain stands as: pending.
Outcome: Not launched as of 2026-09-26. A NASA blog post of 2026-04-23 says Dragonfly is scheduled to launch no earlier than 2028.
Outcome source: NASA Science (Dragonfly blog): NASA’s Dragonfly Rotorcraft Gets Decked Out, Tested (Apr 23, 2026)
Checked against the source on Sep 26, 2026. Report a correction or send a response to this entry
Met · worded as a commitment
Launch · NASA
“Roman is now slated to launch no later than May 2027.”
Said . Source: NASA: NASA Confirms Roman Mission’s Flight Design in Milestone Review (Oct 14, 2021, Editor’s Note, 14 Oct. 2021)
Context: Dated editor’s note (14 Oct. 2021) on a NASA article of 2021-09-29; the replan committed a launch date and a $4.3 billion lifecycle cost. No earlier dated NASA launch date was found (the March 2020 approval article gives none).
Later dated commitments for the same milestone
The counts use the original commitment. The latest date in the chain stands as: met.
Outcome: Roman launched on a Falcon Heavy from Launch Complex 39A at 7:26 a.m. EDT on 2026-08-30; NASA said the launch date had been moved earlier to match the telescope's early completion. (, on or before the deadline)
Outcome source: NASA: NASA's Dark Universe-Seeking Nancy Grace Roman Space Telescope Launches (Aug 30, 2026)
Checked against the source on Sep 26, 2026. Report a correction or send a response to this entry
Open data: download the whole ledger (CSV, CC BY 4.0). Cite as “SpaceNexus Promise Ledger” with a link. How entries are scored: methodology. No sponsor, advertiser or partner can add, remove, reorder, annotate or preview an entry, and these pages carry no advertising.