Artemis program timeline: the US plan to return to the Moon
The only nation to have landed people on the Moon (six landings, 1969–72) flew a crew around it again in April 2026. In February 2026 NASA made Artemis III an Earth-orbit docking test and moved the first landing since 1972 to Artemis IV; in March it paused Gateway and announced a south-pole Moon Base.
Artemis III hardware status (SLS, Orion and the two lander pathfinders) and the latest Artemis news are on the Artemis tracker.
Data reviewed against sources as of · Tracker method v1.0.5 · All dates UTC unless a local time is shown
Official targets
Crewed landing
2028 for Artemis IV
Earlier reading used as a sensitivity: The March 2026 reading, "Early 2028" (NASA ESDMD, 3 Mar 2026; NASA Artemis IV page, last updated 16 Mar 2026; GAO), superseded by NASA's 23 Oct 2026 update, which says "2028"
EO 14369: "establishing initial elements of a permanent lunar outpost by 2030". NASA’s Moon Base phase plan starts long-duration human presence in 2033 or later. No official date for continuous occupation.
L1: A Starship in the lander or tanker configuration reaches orbit (Flight 14 reached orbit on 28 Sep 2026 as a Starlink-configured ship, which does not count on its own) (No official date)
Artemis IV, dated 2028. Four crew; two descend near the lunar south pole. Artemis III, dated 2027 (NASA, 23 Oct 2026: "Launching in 2027"; the Administrator said "summer 2027" the same day), is a crewed docking test with lander pathfinders in Earth orbit, not a landing.
No. A crewed test in low Earth orbit: Orion rendezvous and docking with a Blue Moon Mark 2 human landing system test article and a Starship Version 3 test article (NASA, 23 Oct 2026). Crew: Bresnik, Parmitano (ESA), Douglas, Rubio. Hardware stacking is under way. NASA, 23 Oct 2026: "Launching in 2027". At that day’s briefing the Administrator spoke of a "year-end tanking test and summer 2027 Artemis III launch", and a chart shown there put the mission between May and September (Aerospace America). Earlier wording: "mid-2027" (NASA); "a late 2027 rendezvous" (the Administrator to Congress, 27 Apr 2026). Date: 2027 (NASA, 23 Oct 2026: "Launching in 2027"; the Administrator said "summer 2027" the same day).
The last crew left the lunar surface on 14 Dec 1972 (Apollo 17). Artemis II flew four astronauts around the Moon, launching on 1 Apr 2026. The next planned landings are Artemis IV, dated 2028, and China’s first crewed landing, dated before 2030 (2030年前).
First crewed flight beyond low Earth orbit since 1972: launched 1 Apr 2026 22:35 UTC, flew around the Moon on 6 Apr and splashed down 10 Apr 8:07 pm EDT (11 Apr 00:07 UTC). Set the human distance record, 252,756 miles.
No longer a landing. A crewed test in low Earth orbit: Orion rendezvous and docking with a Blue Moon Mark 2 human landing system test article and a Starship Version 3 test article (NASA, 23 Oct 2026). Crew: Bresnik, Parmitano (ESA), Douglas, Rubio. Hardware stacking is under way. NASA, 23 Oct 2026: "Launching in 2027". At that day’s briefing the Administrator spoke of a "year-end tanking test and summer 2027 Artemis III launch", and a chart shown there put the mission between May and September (Aerospace America). Earlier wording: "mid-2027" (NASA); "a late 2027 rendezvous" (the Administrator to Congress, 27 Apr 2026).
On 20 Sep 2026 the Administrator wrote to NASA staff of "a best-case scenario to launch Artemis III in the summer of 2027" and said "we are ~90 days broken against the Artemis III schedule". The same note aims to "preserve as many as two opportunities for lunar landings in 2028". An internal note, reproduced by NASA Watch (secondary); NASA has not published it.
Unconfirmed (reported but not confirmed by a primary source):
Wikipedia’s "Mk 1.5" name for the Blue Origin vehicle.
The first crewed landing since Apollo 17, near the south pole. Four crew; two descend. NASA has not designated the lander: "lander readiness will determine which provider".
Second landing and the start of base-building; then "at least one surface landing every year". At Ignition NASA described crewed missions about every six months after Artemis IV and V (an aspiration).
SLS sent Orion toward the Moon on Artemis I; on Artemis II it put Orion in a high Earth orbit and Orion’s own engine fired the trans-lunar injection. NASA standardised SLS in February 2026 and dropped the Exploration Upper Stage and Mobile Launcher 2. A ULA Centaur V upper stage was selected through a sole-source justification; GAO (July 2026): a dummy upper stage on Artemis III, the last ICPS on Artemis IV, Centaur V after that. Orion accounts for about 75% of the cumulative overruns in NASA’s major-project portfolio (GAO).
Contracted for the (former) Artemis III and IV landings (about $4.3 billion potential, up 6% since). The architecture needs "more than 10 Starship tankers" per landing (OIG), a tanker every 6 days, and a 12–24-day pad turnaround not yet demonstrated. As of 28 Sep 2026 Starship has flown 14 integrated flight tests: the first 13 were suborbital, and Flight 14 (28 Sep 2026), carrying Starlink satellites, was the first to reach orbit, SpaceX reports. No flight has yet used the lander or tanker configuration. Ship-to-ship propellant transfer, planned for March 2026, has not been attempted; GAO (July 2026) said 2026, and NASA and SpaceX now say early 2027.
Safety (OIG): the design relies on an elevator with no alternative crew ingress; south-pole slopes reach 20° against an 8° post-landing tilt tolerance.
Spaceflight Now describes the tanker count as 10 to 20. In October 2026 a NASA safety panel member put it at about 22 and Elon Musk at 6 to 8; NASA gave no precise number (SpacePolicyOnline; Ars Technica).
Mk2 crew lander: about $3.1 billion crew-lander portion (OIG); critical design review slipping to July 2026 and an uncrewed demo projected for February 2029 before the restructure. A "Blue Moon Mark 2 HLS pathfinder" docks with Orion on Artemis III. The MK1 cargo lander (Moon Base I) waits on New Glenn, which exploded on its pad in May 2026 (a BE-4 main oxygen valve, per Blue Origin); NASA now expects it in the first part of 2027.
GAO (July 2026): key decision point deferred and the suit "does not meet several sizing requirements"; a combined design review is planned for fall 2026. OIG: demonstrations "may not occur until 2031" if delays follow the historical average. On Artemis III NASA plans to fly "a stand-in version of a suit" on the Blue Origin lander (GAO), not a flight suit.
At its 23 Oct 2026 briefing NASA described a simplified, lighter version of the Axiom suit for the first landings, which NASASpaceflight calls the "sortie suit": certified for shorter surface stays and not rated for permanently shadowed regions (CNN; NASASpaceflight). It was first reported in September 2026 (Space Explored, citing Ars Technica; the Administrator’s internal note of 20 Sep 2026, reproduced by NASA Watch). No NASA web page on it found as of 2 Nov 2026.Unconfirmed
NASA (23 Oct 2026): "NASA is targeting two, approximately two-hour long lunar surface Moonwalks during initial surface missions"; astronauts will use them to collect samples and to "test capabilities of the spacesuit provided by Axiom Space".
Unconfirmed (reported but not confirmed by a primary source):
A June 2026 status report that the pressure garments are "fully assembled and undergoing testing" and life-support components "in hand" (secondary).
Phase 1 (now–2028 as presented in March; NASA’s Moon Base manager said on 15 Sep 2026 that it "extends to 2029"): robotic landings, lunar terrain vehicles, the Artemis IV landing. Phase 2 (2029–2032): power, communications, JAXA pressurised rover. Phase 3 (2033 and beyond): long-duration presence with ASI multi-purpose habitats and a CSA utility vehicle. About $20 billion over seven years, as presented (no NASA primary for the figure). Programme executive: Carlos García-Galán.
Unconfirmed (reported but not confirmed by a primary source):
The $20 billion figure has no NASA primary source.
Astrolab CLV-1 ($219M) and Lunar Outpost Pegasus ($220M), delivered by Blue Origin landers. Intuitive Machines was not selected. Four MoonFall scouting drones (designed by NASA JPL; Firefly builds the transfer spacecraft) are targeted to launch in 2028.
Unconfirmed (reported but not confirmed by a primary source):
At least 100 kWe, closed Brayton cycle; ready to launch by Q1 FY2030 (directive) and "ready for launch by 2030" (EO 14369). NASA now calls it Lunar Reactor-1 and says it "will land on the lunar surface in 2030". NASA–DOE MOU January 2026. No prime vendor award found as of September 2026. The separate Space Reactor-1 Freedom is a nuclear-electric propulsion demonstrator on a Mars-flyby mission targeted before the end of 2028; it is not the surface reactor.
Unconfirmed (reported but not confirmed by a primary source):
June 2026 power-converter contracts (Rolls-Royce North America, Brayton Energy, GE).
Paused by NASA "in its current form"; funding redirection pending in Congress
NASA paused Gateway on 24 Mar 2026 and plans to "repurpose applicable Gateway hardware". Congress appropriated $2.6 billion for it in July 2025; the FY2027 request proposes redirecting it. ESA’s I-Hab continues to its critical design review while repurposing is assessed; greater clarity on ESA’s role "could come in December" 2026 at an interim ministerial meeting. GAO: the Power and Propulsion Element "may be repurposed for a future nuclear electric propulsion demonstration".
Unconfirmed (reported but not confirmed by a primary source):
That the Power and Propulsion Element goes specifically to SR-1 Freedom (Wikipedia only).
About $1.9 billion spent on HALO (an OIG report we could not locate).
Four CLPS landers launched 2024–25: Peregrine (failed), IM-1 (landed tilted), Blue Ghost 1 (full success), IM-2 (landed on its side). None has landed in 2026. Next: Griffin-1 (NET November 2026), Blue Moon MK1 and IM-3 (first part of 2027), Blue Ghost 2 (later in 2027), Blue Ghost 3 (2028) and 4 (2029). NASA and Draper ended task order CP-12 in July 2026.
FY2025 enacted $24.8 billion; FY2026 enacted $24.4 billion; FY2027 request $18.8 billion (−23%) including $8.5 billion for Artemis. FY2027 runs on a continuing resolution to 11 Dec 2026.
Missions and programme steps, past and planned. Launch failures are in the full catalogue.
2021
●Done
SpaceX Starship HLS contract (Option A)
Awarded on 16 Apr 2021 (NASA: "total award value is $2.89 billion"). Blue Origin and Dynetics protested to the GAO, which denied both protests on 30 Jul 2021; Blue Origin then sued in the U.S. Court of Federal Claims, which dismissed the case on 4 Nov 2021. The protests and the lawsuit held up work until then, and the OIG says they pushed the Option A delivery date back 6 months, from December 2024 to June 2025. The OIG puts the potential value at about $3 billion. Covered an uncrewed demo and the (former) Artemis III landing.
At least 100 kWe, closed Brayton cycle, awards to up to two providers with an option to down-select at PDR, "readiness to launch by the first quarter of FY30".
VIPER delivery conditionally revived on Blue Moon MK1 #2
$190 million total potential value. The base order covers design and demonstration; the deployment option is decided after Blue Moon MK1’s first flight.
Executive Order 14369, "Ensuring American Space Superiority"
"Returning Americans to the Moon by 2028"; "establishing initial elements of a permanent lunar outpost by 2030"; "a lunar surface reactor ready for launch by 2030".
Artemis restructured: Artemis III becomes an Earth-orbit test; Artemis IV becomes the first landing
NASA: "the Artemis III mission, now in 2027 … to prepare for an Artemis IV landing in 2028", and "at least one surface landing every year thereafter". SLS standardised on the Block 1 configuration.
NASA drops the Exploration Upper Stage; Artemis IV "early 2028", Artemis V "by late 2028"
NASA is "no longer planning to use the Exploration Upper Stage or Mobile Launcher 2". A ULA Centaur V upper stage was selected through a sole-source justification. GAO (July 2026): a dummy upper stage on Artemis III, the single remaining ICPS on Artemis IV, and Centaur V on later missions.
NASA OIG report on the Human Landing System contracts
SpaceX’s lander "will not be ready for a June 2027 lunar landing"; it is "too early to determine the technical feasibility" of acceleration; NASA has no capability to rescue a stranded crew.
Ignition: NASA pauses Gateway and announces a south-pole Moon Base
Gateway paused "in its current form" (GAO); a phased Moon Base at about $20 billion over seven years (as presented, per the Planetary Society); an expanded CLPS with up to 30 robotic landings starting in 2027 (Planetary Society), and a CLPS 2.0 procurement that NASA says is "targeted to be capped at $6 billion" over an anticipated 10-year ordering period.
NASA outlines Artemis III: Orion docks with both landers’ pathfinders in Earth orbit
"Blue Origin’s Blue Moon Mark 2 human landing system pathfinder" and "SpaceX’s Starship human landing system pathfinder"; a non-propulsive spacer replaces the upper stage.
Moon Base awards: two lunar terrain vehicles, lander task orders, MoonFall drones
Astrolab CLV-1 ($219M) and Lunar Outpost Pegasus ($220M), both to be delivered by 2028; Blue Origin task orders ($188M plus a $280.4M option) to deliver them; four MoonFall drones designed by NASA JPL, with Firefly building the spacecraft that carries them to the Moon, launch targeted for 2028. Moon Base I, II and III named.
About 9 pm EDT on 28 May. Blue Origin’s CEO said on 6 Aug that "the anomaly originated at the main oxygen valve on one of the BE-4 engines". LC-36 is New Glenn’s only pad; Blue Moon MK1 slipped to early 2027.
Randy Bresnik (commander), Luca Parmitano (pilot, ESA: "the first time an ESA astronaut has been assigned an Artemis mission"), Andre Douglas, Frank Rubio; backup Bob Hines.
Stacking began in early July. By 7 Sep four of the five segments were stacked on each booster and all four RS-25 engines were installed on the core stage.
HLS cost and schedule baselines "under review"; the lunar suit programme’s key decision point deferred, and the suit "does not meet several sizing requirements".
Suborbital; released 20 Starlink V3 satellites on a path that deorbited them by design. SpaceX: "softest splashdown we have ever had". The booster hit the water harder than planned.
Starship Flight 14: the first Starship to reach orbit
"Splashdown confirmed ... the first orbital flight of Starship" (SpaceX, 28 Sep 2026). Liftoff time from Launch Library 2.
SpaceX reports that the ship entered orbit, deployed all 26 Starlink V3 satellites it carried (all in contact), then made a deorbit burn and splashed down in the Pacific after about 3 hours in orbit; the booster splashed down in the Gulf. The first 13 flights were all suborbital. The ship was Starlink-configured, a variant of the family, so reaching orbit does not move rung L1 on its own (method v1.0.3).
Lander plus Astrolab’s FLIP rover for the Nobile crater region near Mons Mouton, near the south pole, 10 payloads in all; on 15 Sep 2026 NASA expected it to be the only lunar launch of 2026. Falcon Heavy per Spaceflight Now. Voyager Technologies completed its acquisition of Astrobotic on 13 Jul 2026.
Uncrewed cargo pathfinder (not the crew lander) for the Shackleton connecting ridge, carrying NASA’s SCALPSS cameras and a laser retroreflector. The slip followed the New Glenn explosion on its pad in May 2026.
Artemis III: crewed docking test with lander pathfinders in Earth orbit
A planned 14-day mission (NASA, 23 Oct 2026). Blue Origin launches a Blue Moon Mark 2 test article first (it can stay in orbit up to 30 days); Orion launches days later and docks with it, and astronauts spend about two days aboard. Orion then docks with a Starship Version 3 test article in a test "expected to last up to two hours"; the crew will not enter Starship. NASA plans to fly a stand-in version of a suit on the Blue Origin lander (GAO). NASA, 23 Oct 2026: "Launching in 2027". At that day’s briefing the Administrator spoke of a "year-end tanking test and summer 2027 Artemis III launch", and a chart shown there put the mission between May and September (Aerospace America). Earlier wording: "mid-2027" (NASA); "a late 2027 rendezvous" (the Administrator to Congress, 27 Apr 2026).
Unconfirmed (reported but not confirmed by a primary source):
An Orion "internal readiness date" of January 2028 (Wikipedia, no primary).
NASA (23 Oct 2026): both providers must fly an uncrewed demonstration with their crewed landers before the crewed Moon missions, and SpaceX will demonstrate propellant aggregation during it. NASA’s Kelvin Manning said on 20 Oct 2026 that the uncrewed SpaceX landing test is planned for late 2027 (SpacePolicyOnline). OIG (March 2026): SpaceX’s demonstration includes a lunar ascent test, "lifting off the lunar surface and relighting of the Raptor engines", but NASA did not require "an end-to-end ascent, return, and docking"; a NASA safety panel member gave the same picture on 22 Oct 2026, a landing followed by an engine restart, not a return to lunar orbit (SpacePolicyOnline). OIG had expected the demonstration "to slip to the end of 2026" at the earliest. It still depends on ship-to-ship transfer.
Early 2027 (NASA and SpaceX, Oct 2026); was March 2026 (OIG)◇Scheduled
Ship-to-ship cryogenic propellant transfer demonstration
NASA and SpaceX say early 2027; GAO (July 2026) had said 2026
Needed by Starship HLS. Planned for March 2025, then March 2026 (OIG); not attempted in Starship's 14 flights as of 28 Sep 2026 (Flight 14, the first to reach orbit, did not include it). GAO (July 2026) names a long duration flight test and a propellant transfer test as Starship's next major HLS flight milestones: "Both tests are scheduled for 2026." In October 2026 NASA’s Kelvin Manning said SpaceX plans to demonstrate in-space cryogenic transfer in early 2027 (SpacePolicyOnline), and SpaceX President Gwynne Shotwell said the first large-scale in-orbit refuelling demonstration is planned for "early next year" (CBS News; also Ars Technica).
VIPER was cancelled in July 2024 and conditionally revived on 19 Sep 2025. The base task order covers design and demonstration; NASA "will make the decision to exercise that option after the execution and review of the base task and of Blue Origin’s first flight of the Blue Moon MK1 lander", which has slipped to early 2027. On 20 Oct 2026 NASA said VIPER "will embark on a mission to the lunar South Pole region in 2027" and that the rover is "fully built and undergoing final testing"; no decision to exercise the option has been announced. $190M is the total potential value.
Sources:NASA (19 Sep 2025) · NASA (17 Jul 2024) · NASA (20 Oct 2026)
Four crew; two descend near the lunar south pole. NASA: "Lander readiness will determine which provider will safely carry them to the surface": SpaceX Starship HLS or Blue Origin Blue Moon. SpaceX’s existing contract covered the former Artemis III and IV landings.
NASA: "future missions about once per year thereafter". GAO (July 2026): the single remaining ICPS upper stage flies on Artemis IV, and Vulcan Centaur V upper stages on "subsequent missions". Before the February 2026 restructure it was assigned Blue Moon Mk2 with a launch "no later than March 2030" (OIG).
Astrobotic $297.9M for two, Firefly $144.2M, Intuitive Machines $148.3M. Common payloads: SCALPSS, a laser retroreflector and the LETS radiation spectrometer.
Unconfirmed (reported but not confirmed by a primary source):
The mission names "Peregrine M2/M3, IM-6, Blue Ghost M5" are not NASA’s.
Lander not yet designated: "lander readiness will determine which provider". OIG: both providers face challenges that could further affect delivery schedules for a 2028 landing.
February 2029 is a pre-restructure OIG projection (March 2026) for a demonstration of Blue Origin’s "cryogenic propellant transfer capabilities". Under NASA’s 23 Oct 2026 plan Blue Origin defers propellant transfer for its 2028 crewed landing and will "demonstrate the full mission profile in an uncrewed lander transfer stage demonstration mission"; NASA gives no date.
Q1 FY2030 (directive); by 2030 (EO 14369)◇Scheduled
Fission surface reactor ready for launch
Directive: readiness to launch by Q1 FY2030 (Oct–Dec 2029). EO 14369: "a lunar surface reactor ready for launch by 2030". NASA has since named it Lunar Reactor-1 and says it "will land on the lunar surface in 2030". No prime vendor award found as of September 2026.
Claims that appear in reporting but that no primary source confirmed. We show them labelled rather than state them as fact.
Artemis III: Wikipedia’s "Mk 1.5" name for the Blue Origin vehicle.
Axiom AxEMU lunar suit: A June 2026 status report that the pressure garments are "fully assembled and undergoing testing" and life-support components "in hand" (secondary).
Moon Base (announced at the Ignition event): The $20 billion figure has no NASA primary source.
Lunar terrain vehicles and MoonFall: MDA Space as a partner on Pegasus.
Fission Surface Power: June 2026 power-converter contracts (Rolls-Royce North America, Brayton Energy, GE).
Gateway: That the Power and Propulsion Element goes specifically to SR-1 Freedom (Wikipedia only).
Gateway: About $1.9 billion spent on HALO (an OIG report we could not locate).
Lunar communications relay: Intuitive Machines’ Near Space Network lunar relay contract (September 2024, up to $4.82 billion).
Artemis III: crewed docking test with lander pathfinders in Earth orbit: An Orion "internal readiness date" of January 2028 (Wikipedia, no primary).