Program tracker · NASA
For lunar-economy BD teams, investors in the lander companies, and anyone asking whether the commercial Moon deliveries are on schedule.
Sources: NASA Science, CLPS deliveries (May 6, 2026); Aerospace America (AIAA), NASA expects one lunar launch this year, Moon Base manager says (Sep 15, 2026) [secondary]; NASA, Touchdown! Carrying NASA science, Firefly's Blue Ghost lands on Moon (Mar 2, 2025); NASA (release 25-025), NASA receives some data before Intuitive Machines ends lunar mission (Mar 7, 2025); NASA, NASA science, Astrobotic Peregrine Mission One concludes (Jan 18, 2024); NASA, More NASA science, tech will fly to Moon aboard future Firefly flight (Dec 2024); NASA, NASA selects Firefly for new Artemis science, tech delivery to Moon (Jul 2025); ispace, ispace-U.S. update on contract with Draper (Jul 15, 2026); NASA Astronomy Picture of the Day, Odysseus to the Moon (Feb 24, 2024)
Sources: The Planetary Society, 'Ignition': A new series of NASA initiatives (Mar 24, 2026) [secondary]; NASA, Ignition: NASA's plan for the Moon (Mar 24, 2026); SpaceQ, NASA unveils new Moon Base plans, pauses Lunar Gateway (Mar 24, 2026) [secondary]; U.S. GAO (GAO-26-108556), NASA: Assessments of Major Projects (Jul 23, 2026)
Sources: NASA Office of Inspector General (IG-24-013), NASA's Commercial Lunar Payload Services Initiative (Jun 6, 2024)
Sources: NASA, NASA Provides Update on Moon Base Rovers, Landers, Missions (May 26, 2026)
Sources: Aerospace America (AIAA), NASA expects one lunar launch this year, Moon Base manager says (Sep 15, 2026) [secondary]
Curated rows checked against their sources on Sep 27, 2026; database rows (awards, satellites, launches) are read live and cached for an hour. Every fact links its source. Nothing here is sponsored, and no company can pay to change, reorder or preview it. Spotted an error? Report a correction.
Compiled Sep 28, 2026 from 8 public records. Every figure links the record it comes from.
Obligated on USAspending awards matched to the program by our rule
$1.43B on 21 awards
Largest recipient: FIREFLY AEROSPACE INC., $428.9M
Money actually obligated on the rows our rule matches, for the companies we track; an announced ceiling is not obligation. The rule is printed under the awards table.
| Announced | Contractor | What | Value as announced | Award record |
|---|---|---|---|---|
| Jun 30, 2026 | Astrobotic, Firefly Aerospace and Intuitive Machinesfor NASA | Four Moon Base deliveries for late 2028: Astrobotic ($297.9 million, two deliveries), Firefly ($144.2 million), Intuitive Machines ($148.3 million)Task ordersNASA's words: "nearly $600 million". We have not matched these awards to their award IDs. Sources: NASA, NASA Awards More Moon Base Science, Previews New Opportunities (Jun 30, 2026) |
No public data in our pipeline yet: our FFATA subaward table holds no record for this program's award IDs. Primes report first-tier subawards to USAspending, and we will list them here when our subaward sync reaches these awards.
No public data: we have not found a supplier named in a primary-source announcement for this program.
4 payloads catalogued, of which 0 in orbit by GCAT's status code.
Built by: Intuitive Machines LLC (2), Astrobotic Technology Inc. (1), Firefly Aerospace (1).
| Launched | Launch (COSPAR) | Payloads | Count | In orbit | Maker and bus |
|---|---|---|---|---|---|
| Feb 27, 2025 |
2 on the schedule; 0 have slipped at least once since we began recording on Aug 29, 2026. A date is shown only as precisely as the schedule knows it.
| Scheduled | Mission | Rocket | Slip history |
|---|---|---|---|
| Nov 2026 | Falcon Heavy | Griffin Mission OneLaunch Library record | Falcon Heavy | No slip recorded |
| Q1 2027 | Falcon 9 Block 5 | Nova-C IM-3 |
CLPS deliveries are NASA purchases; the lander companies' launch and payload licences are not tracked here.
Commercial Lunar Payload Services (Scheduled)
Four CLPS landers launched 2024–25: Peregrine (failed), IM-1 (landed tilted), Blue Ghost 1 (full success), IM-2 (landed on its side). None has landed in 2026. Next: Griffin-1 (NET November 2026), Blue Moon MK1 and IM-3 (first part of 2027), Blue Ghost 2 (later in 2027), Blue Ghost 3 (2028) and 4 (2029). NASA and Draper ended task order CP-12 in July 2026.
Sources: NASA Science, CLPS deliveries (May 6, 2026); Aerospace America (AIAA), NASA expects one lunar launch this year, Moon Base manager says (Sep 15, 2026) [secondary]; NASA, Touchdown! Carrying NASA science, Firefly's Blue Ghost lands on Moon (Mar 2, 2025)
How this page is built: the contract values under “As announced”, the suppliers, the schedule statements and the context are curated from primary sources and dated. The USAspending awards, GCAT payloads and launches are our own database rows, matched to the program by the rule printed under each table, so a row the rule misses is absent rather than guessed. Cite as “SpaceNexus program tracker: NASA Commercial Lunar Payload Services (CLPS)” with the link and the date you read it.
Contracts announced by the customer or the contractor
18 announced awards
Newest: Astrobotic, Firefly Aerospace and Intuitive Machines, Four Moon Base deliveries for late 2028: Astrobotic ($297.9 million, two deliveries), Firefly ($144.2 million), Intuitive Machines ($148.3 million)
Source: NASA
Announced Jun 30, 2026
Launches flown for the program
1 launch
1 full success, 0 partial, 0 failed
Counted from our Launch Library record, which begins 2024-11-18.
Source: Launch Library 2 (The Space Devs)
Latest Feb 27, 2025
Launches on the schedule
2; 0 slipped
Next: Falcon Heavy | Griffin Mission One, Nov 2026
A slip counts only when both dates were known to the day (the Launch Ledger rule), so a placeholder date rolling forward is not a slip.
Source: Launch Library 2 (The Space Devs)
Schedule read; slips recorded since 2026-08-29 Sep 28, 2026
Payloads in the GCAT catalogue
4 launched; 0 in orbit
Main maker: Intuitive Machines LLC (2)
The catalogue we hold covers launches through 2026-07-11.
Source: GCAT (J. McDowell, planet4589.org)
GCAT file dated Sep 24, 2026
Satellite data from GCAT (J. McDowell, planet4589.org/space/gcat), CC BY 4.0.
APA
SpaceNexus. (2026, September 28). NASA Commercial Lunar Payload Services (CLPS): Program tracker [Data set]. Retrieved September 28, 2026, from https://spacenexus.us/programs/clps
Chicago
SpaceNexus. "NASA Commercial Lunar Payload Services (CLPS): Program tracker." Data as of September 28, 2026. Accessed September 28, 2026. https://spacenexus.us/programs/clps.
BibTeX
@misc{spacenexus_nasacommerciallunarpayloadservic_2026,
author = {{SpaceNexus}},
title = {{NASA Commercial Lunar Payload Services (CLPS)}: Program tracker},
year = {2026},
month = sep,
howpublished = {\url{https://spacenexus.us/programs/clps}},
url = {https://spacenexus.us/programs/clps},
urldate = {2026-09-28},
note = {Data as of 2026-09-28; each fact links its primary source}
}| $590.4 millionannounced total |
| No USAspending record linked |
| May 26, 2026 | Blue Originfor NASA | Task orders CX-2A and CX-2B: deliver the two lunar terrain vehicle rovers to the south-pole regionTwo task orders under the first CLPS contractNASA: "$188 million with an option period worth $280.4 million". The second order is 80JSC026F7015. NASA's release does not name the lander model. Sources: NASA, NASA Provides Update on Moon Base Rovers, Landers, Missions (May 26, 2026) | $188 millionannounced total | 80JSC026F7013 |
| Sep 19, 2025 | Blue Originfor NASA | Task order CS-7: VIPER on a second Blue Moon MK1 (base: accommodation and off-load demonstration; option: delivery)Task orderNASA's words: "total potential value". Sources: NASA, NASA Selects Blue Origin to Deliver VIPER Rover to Moon's South Pole (Sep 19, 2025) | $190 millionpotential | 80JSC025F7071 |
| Jul 29, 2025 | Firefly Aerospacefor NASA | Task order CS-6: Blue Ghost Mission 4 to the south-pole region, with two rovers and three instrumentsTask order Sources: NASA, NASA Selects Firefly for New Artemis Science, Tech Delivery to Moon (Jul 29, 2025) | $176.7 millionannounced total | 80JSC025F7057 |
| Dec 18, 2024 | Firefly Aerospacefor NASA | Task order CP-21: Blue Ghost Mission 3 to the Gruithuisen DomesTask order Sources: NASA, More NASA Science, Tech Will Fly to Moon Aboard Future Firefly Flight (Dec 18, 2024); NASA Science, CLPS Deliveries (May 6, 2026) | $179 millionannounced total | 80JSC025F7026 |
| Aug 29, 2024 | Intuitive Machinesfor NASA | Task order CP-22: six payloads to Mons Mouton near the south poleTask order Sources: NASA, NASA Awards Intuitive Machines Lunar South Pole Research Delivery (Aug 29, 2024); NASA Science, CLPS Deliveries (May 6, 2026) | $116.9 millionannounced total | 80JSC024F0079 |
| Mar 14, 2023 | Firefly Aerospacefor NASA | Task order CS-3: Blue Ghost Mission 2 to the far side, with ESA's Lunar Pathfinder relayTask orderNASA's words: "just under $112 million". With the related order CS-4 the Inspector General gives $129.9 million. Sources: NASA, NASA Picks Firefly Aerospace for Robotic Delivery to Far Side of Moon (Mar 14, 2023); NASA Office of Inspector General (IG-24-013), NASA's Commercial Lunar Payload Services Initiative (Jun 6, 2024); NASA Science, CLPS Deliveries (May 6, 2026) | $112 millionannounced total | 80JSC023F0041 |
| Jul 21, 2022 | Draperfor NASA | Task order CP-12: Schrodinger basin on the far side (ispace-U.S. APEX 1.0 lander)Task orderNASA's 2022 release named Draper's SERIES-2 lander; NASA's CLPS page lists the mission as Team Draper, ispace APEX 1.0. In July 2026 ispace-U.S. said Draper had mutually agreed with NASA to end task order CP-12. Sources: NASA, NASA Selects Draper to Fly Research to Far Side of Moon (Jul 21, 2022); NASA Science, CLPS Deliveries (May 6, 2026); ispace, ispace-U.S. Update on Contract with Draper (Jul 15, 2026) | $73 millionannounced total | 80JSC022F0174 |
| Nov 17, 2021 | Intuitive Machinesfor NASA | Task order CP-11: Reiner Gamma (IM-3)Task order Sources: NASA, NASA Selects Intuitive Machines for New Lunar Science Delivery (Nov 17, 2021); NASA Science, CLPS Deliveries (May 6, 2026) | $77.5 millionannounced total | 80JSC022F0022 |
| Feb 4, 2021 | Firefly Aerospacefor NASA | Task order TO19D: Blue Ghost Mission 1 to Mare CrisiumTask orderThe Inspector General gives $101.5 million current. Sources: NASA, NASA Selects Firefly Aerospace for Artemis Commercial Moon Delivery in 2023 (Feb 4, 2021); NASA Office of Inspector General (IG-24-013), NASA's Commercial Lunar Payload Services Initiative (Jun 6, 2024) | $93.3 millionannounced total | 80JSC021F0098 |
| Oct 16, 2020 | Intuitive Machinesfor NASA | PRIME-1 drill delivery (flew on IM-2)Task orderNASA announced "approximately $47 million"; the Inspector General gives $50.0 million current. PRIME-1 flew on IM-2, which landed on its side in March 2025. Sources: NASA, NASA Selects Intuitive Machines to Land Water-Measuring Payload on the Moon (Oct 16, 2020); NASA Office of Inspector General (IG-24-013), NASA's Commercial Lunar Payload Services Initiative (Jun 6, 2024); NASA, NASA Receives Some Data Before Intuitive Machines Ends Lunar Mission (Mar 7, 2025) | $47 millionannounced total | 80JSC021F0004 |
| Jun 11, 2020 | Astroboticfor NASA | Task order TO20A: Griffin lander to deliver the VIPER roverTask orderNASA added $67.8 million in July 2022 and said the contract then totalled $320.4 million; the Inspector General gives $322.8 million. NASA cancelled VIPER on July 17, 2024; Griffin Mission One continues under this contract without the rover. VIPER was later assigned to Blue Origin (task order CS-7, below). Sources: NASA, NASA Selects Astrobotic to Fly Water-Hunting Rover to the Moon (Jun 11, 2020); NASA, NASA Replans CLPS Delivery of VIPER to 2024 to Reduce Risk (Jul 18, 2022); NASA Office of Inspector General (IG-24-013), NASA's Commercial Lunar Payload Services Initiative (Jun 6, 2024); NASA, NASA Ends VIPER Project, Continues Moon Exploration (Jul 17, 2024) | $199.5 millionannounced total | 80JSC020F0220 |
| Apr 8, 2020 | Masten Space Systemsfor NASA | Task order TO19C: eight NASA payloads to the lunar surface (Masten filed for bankruptcy in July 2022)Task orderValue is the Inspector General's initial figure; the date is the USAspending start date. NASA paid $66.1 million. Sources: NASA Office of Inspector General (IG-24-013), NASA's Commercial Lunar Payload Services Initiative (Jun 6, 2024) | $75.9 millionannounced total | 80JSC020F0262 |
| Nov 18, 2019 | Five companiesfor NASA | Five more vendors join CLPS: Blue Origin, Ceres Robotics, Sierra Nevada Corporation, SpaceX and TyvakIDIQ on-ramp, through November 2028The same $2.6 billion combined maximum, now across 14 vendors. Award IDs 80JSC020D0010 to 80JSC020D0014. Sources: NASA, New Companies Join Growing Ranks of NASA Partners for Artemis Program (Nov 18, 2019) | $2.6 billioncombined maximum | No USAspending record linked |
| May 31, 2019 | Astroboticfor NASA | Task order TO2-AB: Peregrine Mission OneTask orderThe Inspector General gives a current value of $107.9 million (February 2024). Sources: NASA, NASA Selects First Commercial Moon Landing Services for Artemis Program (May 31, 2019); NASA Office of Inspector General (IG-24-013), NASA's Commercial Lunar Payload Services Initiative (Jun 6, 2024); NASA Science, CLPS Deliveries (May 6, 2026) | $79.5 millionannounced total | 80JSC019F0164 |
| May 31, 2019 | Intuitive Machinesfor NASA | Task order TO2-IM: IM-1Task orderWith two related orders the Inspector General gives $81.7 million initial and $122.0 million current. Sources: NASA, NASA Selects First Commercial Moon Landing Services for Artemis Program (May 31, 2019); NASA Office of Inspector General (IG-24-013), NASA's Commercial Lunar Payload Services Initiative (Jun 6, 2024); NASA Science, CLPS Deliveries (May 6, 2026) | $77 millionannounced total | 80JSC019F0165 |
| May 31, 2019 | Orbit Beyondfor NASA | Task order TO2: a 2020 delivery (the company withdrew in July 2019)Task orderNothing was obligated. Sources: NASA, NASA Selects First Commercial Moon Landing Services for Artemis Program (May 31, 2019); NASA Office of Inspector General (IG-24-013), NASA's Commercial Lunar Payload Services Initiative (Jun 6, 2024) | $97 millionannounced total | 80JSC019F0167 |
| Nov 29, 2018 | Nine companiesfor NASA | CLPS vendor contracts, 10 years: Astrobotic, Deep Space Systems, Draper, Firefly, Intuitive Machines, Lockheed Martin Space, Masten, Moon Express and Orbit BeyondIndefinite-delivery, indefinite-quantity (IDIQ)Award IDs 80HQTR19D0005, 0007, 0009, 0010, 0014, 0015, 0016, 0018 and 0019. USAspending lists a ceiling of $4.2 billion on most of these vehicles; we found no NASA statement of a ceiling increase. Sources: NASA, NASA Announces New Partnerships for Commercial Lunar Payload Delivery Services (Nov 29, 2018) | $2.6 billioncombined maximum | No USAspending record linked |
NASA buys CLPS deliveries as task orders under 14 vendor contracts. The USAspending total below is a floor: it counts only what our mirror holds for the companies we track.
21 award records with $1.43 billion obligated, dated May 30, 2019 to May 26, 2026. Obligated means money actually put on contract, not an announced ceiling. Newest row read from USAspending on Sep 24, 2026.
| Recipient | Awards | Obligated |
|---|---|---|
| FIREFLY AEROSPACE INC. | 5 | $428.9 million |
| ASTROBOTIC TECHNOLOGY INC | 3 | $414.8 million |
| INTUITIVE MACHINES, LLC | 7 | $400 million |
| BLUE ORIGIN, LLC | 4 | $137.7 million |
| THE CHARLES STARK DRAPER LABORATORY, INC. | 1 | $43.3 million |
| LOCKHEED MARTIN CORP | 1 | $599,962 |
| Award ID | Recipient | Description (the government's words) | Date | Obligated |
|---|---|---|---|---|
| 80JSC020F0220 | ASTROBOTIC TECHNOLOGY INC | VOLATILES INVESTIGATING POLAR EXPLORATION ROVER (VIPER) DELIVERY | Jun 11, 2020 | $314 million |
| 80JSC019F0165 |
An indefinite-delivery vehicle's own amount is the sum of the orders placed under it, and those orders are counted above, so vehicles are listed but never added.
Our USAspending mirror is filled company by company for the 323 companies we track, so awards to anyone else are not in it. Rule: USAspending contract rows from NASA's CLPS contracting offices (award IDs beginning 80JSC and the 80HQTR19D vendor contracts) whose own description names CLPS or Commercial Lunar Payload Services, plus the task orders NASA announced as CLPS deliveries, listed by award ID. Any other task order whose description does not say CLPS is left out, so the total is a floor. Grants that mention CLPS are not counted. Source: USAspending.gov (US Treasury).
| 2025-038 |
| IM-2 Athena |
| 1 |
| 0 |
| Intuitive Machines LLCNova-C |
| Jan 15, 2025 | 2025-010 | Blue Ghost | 1 | 0 | Firefly AerospaceBlue Ghost |
| Feb 15, 2024 | 2024-030 | IM-1 Odysseus | 1 | 0 | Intuitive Machines LLCNova-C |
| Jan 8, 2024 | 2024-006 | Peregrine Mission One | 1 | 0 | Astrobotic Technology Inc.Peregrine |
Rule: GCAT payloads on lunar trajectories (GCAT orbit code CLO) owned by the CLPS lander companies, launched since 2023. The catalogue we hold covers launches through Jul 11, 2026 (GCAT file dated Sep 24, 2026); later launches are not in it yet. Satellite data from GCAT (J. McDowell, planet4589.org/space/gcat), CC BY 4.0. GCAT.
| Falcon 9 Block 5 |
| No slip recorded |
1 flown in our record (it begins Nov 18, 2024): 1 success, 0 partial failures, 0 failures. Launch outcomes are the launch vehicle's, as Launch Library records them.
| Launched | Mission | Rocket | Outcome |
|---|---|---|---|
| Feb 27, 2025 | Falcon 9 Block 5 | Nova-C IM-2 & OthersLaunch Library record | Falcon 9 Block 5 | Success |
Rule: Launch Library launches whose name carries a CLPS lander (Nova-C, IM-n, Griffin, Blue Ghost, Blue Moon MK1, Peregrine). Slips use the Launch Ledger rule: a move counts only when both dates were known to the day, so a placeholder rolling from one month or year to the next is never a slip. Schedule data from Launch Library 2 (The Space Devs).
Lunar communications relay (Scheduled)
No US lunar relay is operating. ESA’s Lunar Pathfinder relay rides on Blue Ghost 2 (later in 2027). CAPSTONE and LRO are not relays.
Unconfirmed: Intuitive Machines’ Near Space Network lunar relay contract (September 2024, up to $4.82 billion).
Sources: Firefly Aerospace, Blue Ghost Mission 2 (Sep 24, 2026); Aerospace America (AIAA), NASA expects one lunar launch this year, Moon Base manager says (Sep 15, 2026) [secondary]; NASA Science, CLPS deliveries (May 6, 2026)
| Mission | Company | Launch | Status and outcome |
|---|---|---|---|
| Peregrine Mission One | Astrobotic (NASA CLPS) | 8 Jan 2024 | Done: Failure |
| IM-1 Odysseus | Intuitive Machines (NASA CLPS) | 15 Feb 2024 | Done: Partial success |
| Blue Ghost Mission 1 | Firefly Aerospace (NASA CLPS) | 15 Jan 2025 | Done: Success |
| IM-2 Athena | Intuitive Machines (NASA CLPS) | 27 Feb 2025 | Done: Partial success |
| Griffin Mission One ("Moon Base II") | Astrobotic, a Voyager Technologies company (NASA CLPS) | No earlier than November 2026 (NASA Moon Base manager, 15 Sep 2026) | Scheduled |
| Blue Moon MK1 "Endurance" ("Moon Base I") | Blue Origin (NASA CLPS) | First part of 2027 (NASA, 15 Sep 2026; was "no earlier than fall 2026") | Scheduled |
| IM-3 Nova-C "Trinity" ("Moon Base III") | Intuitive Machines (NASA CLPS) | First part of 2027 (NASA); first quarter of 2027 (Intuitive Machines CEO) | Scheduled |
| Blue Ghost Mission 2 | Firefly Aerospace (NASA CLPS) | Later in 2027 (NASA, 15 Sep 2026) | Scheduled |
| IM-4 (CP-22) | Intuitive Machines (NASA CLPS) | NET 2027 (NSSDCA) | Scheduled |
| Blue Moon MK1 #2 with VIPER | Blue Origin / NASA | Late 2027 (NASA, Sep 2025), conditional | Scheduled |
| Blue Ghost Mission 3 (CP-21) | Firefly Aerospace (NASA CLPS) | 2028 (NASA award, Dec 2024) | Scheduled |
| Blue Ghost Mission 4 (CS-6) | Firefly Aerospace (NASA CLPS) | Landing targeted in 2029 (NASA award, Jul 2025) | Scheduled |
| IM-5, Intuitive Machines Nova-D (CT-4) | Intuitive Machines (NASA CLPS) | No date | Scheduled |
| Four CLPS deliveries awarded 30 Jun 2026 | Astrobotic (2), Firefly, Intuitive Machines | Late 2028 (NASA, 30 Jun 2026) | Scheduled |
From the Moon mission catalogue, where each row carries its sources.
19 Sep 2025 VIPER delivery conditionally revived on Blue Moon MK1 #2 (Done)
$190 million total potential value. The base order covers design and demonstration; the deployment option is decided after Blue Moon MK1’s first flight.
Sources: NASA, NASA selects Blue Origin to deliver VIPER rover to Moon's south pole (Sep 19, 2025)
24 Mar 2026 Ignition: NASA pauses Gateway and announces a south-pole Moon Base (Done)
Gateway paused "in its current form"; a phased Moon Base at about $20 billion over seven years (as presented, per the Planetary Society); an expanded CLPS of "up to 30 robotic landings starting in 2027" for roughly $6 billion over a decade.
Sources: NASA, Ignition: NASA's plan for the Moon (Mar 24, 2026); The Planetary Society, Ignition: new NASA initiatives (Mar 2026) [secondary]; SpaceQ, NASA unveils new Moon Base plans, pauses Lunar Gateway (Mar 24, 2026) [secondary]; U.S. GAO (GAO-26-108556), NASA: Assessments of Major Projects (Jul 23, 2026)
26 May 2026 Moon Base awards: two lunar terrain vehicles, lander task orders, MoonFall drones (Done)
Astrolab CLV-1 ($219M) and Lunar Outpost Pegasus ($220M), both to be delivered by 2028; Blue Origin task orders ($188M plus a $280.4M option) to deliver them; four MoonFall drones designed by NASA JPL, with Firefly building the spacecraft that carries them to the Moon, launch targeted for 2028. Moon Base I, II and III named.
Sources: NASA (release 26-046), NASA provides update on Moon Base rovers, landers, missions (May 26, 2026); SpacePolicyOnline, NASA awards initial Moon Base rover and lander contracts (May 26, 2026) [secondary]; Astrolab, NASA selects Astrolab to provide lunar rover (May 26, 2026)
30 Jun 2026 Four more CLPS deliveries awarded for late 2028 (Done)
Sources: NASA, NASA awards more Moon Base science, previews new opportunities (Jun 30, 2026); Via Satellite, Astrobotic, Firefly and Intuitive Machines win NASA lunar delivery missions (Jun 30, 2026) [secondary]
15 Sep 2026 NASA expects only one lunar launch in 2026 (Griffin-1) (Done)
Sources: Aerospace America (AIAA), NASA expects one lunar launch this year, Moon Base manager says (Sep 15, 2026) [secondary]
These rows are the Race to the Moon tracker's, shown here unchanged; its audit keeps them current.
| INTUITIVE MACHINES, LLC |
| LUNAR SURFACE TRANSPORTATION-NASA PROVIDED LUNAR PAYLOAD (NPLP) DELIVERY |
| May 30, 2019 |
| $116.9 million |
| 80JSC023F0041 | FIREFLY AEROSPACE INC. | COMMERCIAL LUNAR PAYLOAD SERVICES (CLPS) TASK ORDER CS-3 | Mar 14, 2023 | $112.8 million |
| 80JSC021F0098 | FIREFLY AEROSPACE INC. | ENHAMCED LANDING AND MONILITY STUDY | Feb 4, 2021 | $110.6 million |
| 80JSC025F7026 | FIREFLY AEROSPACE INC. | COMMERCIAL LUNAR PAYLOAD SERVICES (CLPS) | Dec 18, 2024 | $108.2 million |
| 80JSC019F0164 | ASTROBOTIC TECHNOLOGY INC | LUNAR SURFACE TRANSPORTATION SERVICES - NASA-PROVIDED LUNAR PAYLOAD (NPLP) DELIVERY | May 30, 2019 | $100.2 million |
| 80JSC024F0079 | INTUITIVE MACHINES, LLC | COMMERCIAL LUNAR PAYLOAD SERVICES (CLPS) | Aug 29, 2024 | $89.9 million |
| 80JSC022F0022 | INTUITIVE MACHINES, LLC | CLPS TASK ORDER CP-11 CLPS PAYLOADS AND RESEARCH INVESTIGATIONS ON THE SURFACE OF THE MOON | Nov 17, 2021 | $85.6 million |
| 80JSC025F7057 | FIREFLY AEROSPACE INC. | COMMERCIAL LUNAR PAYLOAD SERVICES (CLPS) CONTRACT TASK ORDER CS-6. | Jul 29, 2025 | $77.9 million |
| 80JSC021F0004 | INTUITIVE MACHINES, LLC | COMMERCIAL LUNAR PAYLOAD SERVICES (CLPS) TASK ORDER (TO) POLAR RESOURCE ICE-MINING EXPERIMENT-1 (PRIME-1) LUNAR SURFACE PAYLOAD DELIVERY -LUNAR POLE | Oct 16, 2020 | $56.3 million |
| 80JSC025F7071 | BLUE ORIGIN, LLC | COMMERCIAL LUNAR PAYLOAD SERVICES (CLPS) CONTRACT TASK ORDER CS-7 | Sep 16, 2025 | $55.1 million |
| 80JSC026F7009 | INTUITIVE MACHINES, LLC | CLPS TASK ORDER CT-4 PAYLOADS AND RESEARCH INVESTIGATIONS ON THE SURFACE OF THE MOON. | Mar 25, 2026 | $46.8 million |
| 80JSC022F0174 | THE CHARLES STARK DRAPER LABORATORY, INC. | COMMERCIAL LUNAR PAYLOAD SERVICES (CLPS)TASK ORDER CP-12 CLPS PAYLOADS AND RESEARCH INVESTIGATIONS ON THE SURFACE OF THE MOON | Jul 21, 2022 | $43.3 million |
| 80JSC026F7015 | BLUE ORIGIN, LLC | COMMERCIAL LUNAR PAYLOAD SERVICES (CLPS) CONTRACT TASK ORDER CX-2B | May 26, 2026 | $32 million |
| 80JSC026F7013 | BLUE ORIGIN, LLC | COMMERCIAL LUNAR PAYLOAD SERVICES (CLPS) CONTRACT TASK ORDER CX-2A | May 26, 2026 | $32 million |
| 80JSC023F0108 | FIREFLY AEROSPACE INC. | COMMERCIAL LUNAR PAYLOAD SERVICES (CLPS) | Aug 25, 2023 | $19.3 million |
| 80JSC024F0068 | BLUE ORIGIN, LLC | COMMERCIAL LUNAR PAYLOAD SERVICES (CLPS) TASK ORDER CT-3 | Jul 24, 2024 | $18.7 million |
| 80JSC020F0285 | INTUITIVE MACHINES, LLC | CLPS TO 20C, RADIO FREQUENCY MASS GAUGE AND INTEGRATION AND CRYOGENIC DATA DELIVERY | Jul 31, 2020 | $4 million |
| 80JSC025F7061 | LOCKHEED MARTIN CORP | CX-1 CLPS TRADE STUDY MID-SIZED LANDER CAPABILITY ASSESSMENT LOCKHEED MARTIN BASE AWARD | Jul 16, 2025 | $599,962 |
| 80JSC025F7055 | ASTROBOTIC TECHNOLOGY INC | CX-1 CLPS TRADE STUDY MID-SIZED LANDER CAPABILITY ASSESSMENT ASTROBOTIC BASE AWARD | Jul 16, 2025 | $588,058 |
| 80JSC021F0229 | INTUITIVE MACHINES, LLC | CLPS TO 20C, RADIO FREQUENCY MASS GAUGE AND INTEGRATION AND CRYOGENIC DATA DELIVERY | Jun 16, 2021 | $432,000 |